Multiple Choice
When requesting "worst case" design analysis, you expect the reliability group to
A) Analyze the worst rejects.
B) Analyze only those products failing to meet specification requirements.
C) Determine whether product requirements can be met with subassemblies assumed at their worst combination of tolerances.
D) Assume all subassembly tolerances at their maximum limit.