Question 61
Multiple Choice
The ________ variance is the difference between the earned value and the actual costs for the work completed to date.
Question 62
True/False
A Control Chart can be used to estimate schedule trends.
Question 63
True/False
Progress and performance can be measured quantitatively as well as qualitatively.
Question 64
Multiple Choice
A negative cost variance combined with a negative schedule variance is an indicator of
Question 65
True/False
A project manager would be glad to see a TCPI of 1.2.
Question 66
Multiple Choice
A program financial accountant learns that a project is currently earning $1.15 for each dollar actually spent. The accountant is able to determine this by looking at the
Question 67
Multiple Choice
Which of the following is not one of the four steps for measuring and evaluating project performance?
Question 68
Multiple Choice
Which of the following is not a benefit of Earned Value Management?
Question 69
True/False
The PCIC index measures the project percent complete in relation to the actual resources used so far on the project.
Question 70
Multiple Choice
The _________ index measures the project percent complete in relation to the resources that were budgeted.
Question 71
Essay
Identify and describe two methods for tracking and trending schedule performance.
Question 72
True/False
For a more complex project, statistical analysis can be applied to a control chart to identify potential causes of schedule deviation.
Question 73
Multiple Choice
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the