Question 61
True/False
High setup costs favor producing in small batches.
Question 62
Multiple Choice
You would like to use the fixed-time-period inventory model to compute the desired order quantity for a company. You know that vendor lead time is 5 days and the number of days between reviews is 7. Which of the following is the standard deviation of demand over the review and lead time if the standard deviation of daily demand is 8?
Question 63
True/False
In the fixed-time period model it is necessary to determine the inventory currently on hand to calculate the size of the order to place with a vendor.
Question 64
True/False
Price-break models deal with the fact that the selling price of an item generally increases as the order size increases.
Question 65
Multiple Choice
Using the fixed-time-period inventory model, and given an average daily demand of 200 units, 4 days between inventory reviews, 5 days for lead time, 120 units of inventory on hand, a z of 1.96, and a standard deviation of demand over the review and lead time of 3 units, which of the following is the order quantity?
Question 66
Multiple Choice
The Pareto principle is best applied to which of the following inventory systems?
Question 67
True/False
Safety stock can be computed when using the fixed-order quantity inventory model by multiplying a z value representing the number of standard deviations to achieve a service level or probability by the standard deviation of periodic demand.
Question 68
True/False
When stocked items are sold, the optimal inventory decision using marginal analysis is to stock that quantity where the probable profit from the sale or use of the last unit is equal to or greater than the probable losses if the last unit remains unsold.
Question 69
True/False
The "sawtooth effect" is named after the jagged shape of the graph of inventory levels over time.
Question 70
Multiple Choice
You would like to use the fixed-time period inventory model to compute the desired order quantity for a company. You know that vendor lead time is 10 days and the number of days between reviews is 15. Which of the following is the standard deviation of demand over the review and lead time period if the standard deviation of daily demand is 10?
Question 71
Multiple Choice
In making any decision that affects inventory size, which of the following costs do not need to be considered?
Question 72
Multiple Choice
Which of the following is not included as an inventory holding cost?
Question 73
True/False
The fixed-order quantity inventory model is more appropriate for important items such as critical repair parts because there is closer monitoring and, therefore, quicker response to a potential stock out.
Question 74
Multiple Choice
Using the simple order quantity model in an inventory control problem, Kathy calculated the order quantity to be 1,000 units. In a review, she found out that the demand is actually double that of the quantity she had used and the holding cost is only half that of the value she used. The new economic order quantity using the correct data will be
Question 75
Multiple Choice
Using the fixed-time-period inventory model, and given an average daily demand of 75 units, 10 days between inventory reviews, 2 days for lead time, 50 units of inventory on hand, a service probability of 95 percent, and a standard deviation of demand over the review and lead time of 8 units, which of the following is the order quantity?
Question 76
Multiple Choice
Which of the following is not a reason to carry inventory?
Question 77
True/False
In a price-break model of lot sizing, to find the lowest-cost order quantity, it is sometimes necessary to calculate the economic order quantity for each possible price and to check to see whether the lowest cost quantity is feasible.