When There Is a Significant Increase in the Estimated Total

Question 1

Multiple Choice

When there is a significant increase in the estimated total contract costs but the increase does not eliminate all profit on the contract, which of the following is correct?


A) Under both the percentage-of-completion and the completed-contract methods, the estimated cost increase requires a current period adjustment of excess gross profit recognized on the project in prior periods.
B) Under the percentage-of-completion method only, the estimated cost increase requires a current period adjustment of excess gross profit recognized on the project in prior periods.
C) Under the completed-contract method only, the estimated cost increase requires a current period adjustment of excess gross profit recognized on the project in prior periods.
D) No current period adjustment is required.