Multiple Choice
All of the following activities are appropriate upon completion of risk response planning EXCEPT:
A) The risk register should be updated to reflect the risk response strategies.
B) The risk register should be baselined after planning is completed, and should not be updated once the project is in flight.
C) The risk register should be updated to reflect any changes to the project schedule, budget or resource assignments.
D) A single person should be assigned as the owner of each risk response strategy.
Correct Answer:

Verified
Correct Answer:
Verified
Q6: Identify and describe 3 risk identification techniques.
Q7: Sometimes the risks posed by a project
Q9: All of the following describe an appropriate
Q10: The risk register is a living document
Q12: Which of the following describes the effective
Q14: The primary questions project teams use in
Q15: Project managers can identify risks by learning
Q16: All of the following are among the
Q19: A risk management plan should define who
Q38: Risk response strategies such as acceptance and