Multiple Choice
Project managers can identify risks by learning and understanding the cause and effect relationships that bear on risk events. All of the following approaches rely upon an understanding of cause and effect relationships to identify risks EXCEPT:
A) develop a flow chart that shows how data flows from one person to another
B) conduct a root cause analysis
C) examine triggers that a risk is about to occur
D) list all risks in a risk register
Correct Answer:

Verified
Correct Answer: