Multiple Choice
A milestone is a typical measuring point used when establishing cost control. Which of the following accurately describes the use of cost control milestones?
A) Project managers can use their cash flow projections to determine the funding needed to reach each milestone.
B) Project managers and sponsors often decide the number of milestones jointly.
C) Milestones are often identified in the project charter.
D) all of these
Correct Answer:

Verified
Correct Answer:
Verified