Exam 15: Project Management Online
Exam 1: Introduction to Modeling and Decision Analysis78 Questions
Exam 2: Introduction to Optimization and Linear Programming76 Questions
Exam 3: Modeling and Solving Lp Problems in a Spreadsheet93 Questions
Exam 4: Sensitivity Analysis and the Simplex Method76 Questions
Exam 5: Network Modeling92 Questions
Exam 6: Integer Linear Programming102 Questions
Exam 7: Goal Programming and Multiple Objective Optimization81 Questions
Exam 8: Nonlinear Programming Evolutionary Optimization87 Questions
Exam 9: Regression Analysis93 Questions
Exam 10: Data Mining125 Questions
Exam 11: Time Series Forecasting125 Questions
Exam 12: Introduction to Simulation Using Analytic Solver Platform85 Questions
Exam 13: Queuing Theory97 Questions
Exam 14: Decision Analysis125 Questions
Exam 15: Project Management Online82 Questions
Select questions type
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
-A weakness of Gantt charts is that they do not explicitly
(Multiple Choice)
4.9/5
(76)
What are the immediate successors of activity D in this network?
(Multiple Choice)
4.7/5
(73)
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
-Slack represents the amount of time by which an activity can be delayed without delaying the entire project, assuming that
(Multiple Choice)
4.7/5
(76)
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
-What is the earliest start time for activity D in the following diagram?
(Multiple Choice)
4.8/5
(90)
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.
-Two network design techniques used in Project Management are: the Activity-On-Node (AON) and the Activity on Arcs (AOA).
(True/False)
4.8/5
(75)
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
-Refer to Exhibit 15.5. If the following project must be completed by day 18 at minimum cost how do we change the LP model?
(Short Answer)
4.8/5
(93)
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. What formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis? 
(Essay)
4.8/5
(73)
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
-In a PERT network the time required to complete a path is a(n)
(Multiple Choice)
4.7/5
(79)
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.
-In deciding which activities to crash, select
(Multiple Choice)
4.8/5
(72)
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
-Slack for activity I is computed as
(Multiple Choice)
4.9/5
(73)
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
-The purpose of the backward pass in the Critical Path Method (CPM) technique is to
(Multiple Choice)
4.9/5
(79)
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
-Refer to Exhibit 15.5. What formula should go in cell H3 of the Costs spreadsheet to compute Crash Cost Per Day?
(Short Answer)
4.8/5
(88)
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set of activities:
-Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity A to the node for activity C?
(Essay)
4.9/5
(74)
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.
-In a project network there must be a unique critical path.
(True/False)
4.8/5
(68)
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.4. Identify each path through the network and its expected length.
(Short Answer)
4.7/5
(84)
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack? 
(Essay)
4.7/5
(87)
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
-The term "time zero" identifies
(Multiple Choice)
4.9/5
(84)
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.
-Slack is the amount of time by which the start of an activity can be delayed without delaying the project.
(True/False)
4.9/5
(76)
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set of activities:
-Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity F to the node for activity I?
(Essay)
4.8/5
(89)
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
-Non-critical activities are distinguished by the presence of
(Multiple Choice)
4.9/5
(88)