Exam 10: Monitoring and Information Systems

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The best sources of items to be monitored are the project risk management plan,change of scope orders,and __________.

(Multiple Choice)
4.9/5
(77)

Reports for __________ have a need for detailed information about individual tasks and the factors affecting such tasks.

(Multiple Choice)
4.8/5
(78)

If EV = $500,AC = $475,PV = $450; SV = ________.

(Multiple Choice)
4.8/5
(88)

__________ can often give the project manager early warning signals of potential problems in a project and help understand the relationships of individual tasks to one another and to the overall project.

(Multiple Choice)
4.8/5
(79)

A(n)__________ is a simple tally of the occurrence of an event.This type of measure is easy to collect and is often reported as events per unit of time or reported as events as a percent of a standard number.

(Multiple Choice)
4.9/5
(87)

If CSI is less than 1,it is indicative of a(n)__________.

(Multiple Choice)
4.7/5
(79)

In earned value analysis,the 50-50 rule assumes that __________.

(Multiple Choice)
4.9/5
(79)

If CPI = 1.05,then __________ is favorable.

(Multiple Choice)
4.9/5
(80)

In earned value analysis,the 0 - 100 percent rule allows __________.

(Multiple Choice)
4.9/5
(73)

__________ is collecting,recording,and reporting information concerning any and all aspects of project performance that the project manager or others in the organization wish to know.

(Multiple Choice)
4.7/5
(87)

Measuring characteristics such as "quality of team member cooperation" and "morale of team members" generally takes the form of __________characterizations.

(Multiple Choice)
4.8/5
(83)

The project control process should be viewed as a(n)__________,with revised plans and schedules (if warranted)following corrective actions.The project control process should run continuously until the project is completed.

(Multiple Choice)
4.8/5
(81)

Identify some of the benefits when timely reports are delivered to the proper people by the project management information system.

(Essay)
4.9/5
(86)

A(n)__________ can be used to deal with issues of honesty related to the monitoring system.

(Multiple Choice)
4.8/5
(79)

For each factor to be measured during monitoring; performance criteria,standards,and __________ should be established.

(Multiple Choice)
4.8/5
(80)
Showing 41 - 55 of 55