Exam 5: Developing the Schedule

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Having the person who will be responsible for performing a specific activity estimate the duration for that activity __________ from that person and _________ that may be introduced by having one person estimate the durations for all of the activities.

(Multiple Choice)
4.9/5
(73)

The sponsor or customer often states the project required completion time in the project charter, RFP, or contract.

(True/False)
4.9/5
(81)

Earliest finish time (EF) is the earliest time by which a specific activity can be completed, calculated

(Multiple Choice)
4.8/5
(76)

This longest path in the overall network diagram is called the network path.

(True/False)
4.8/5
(79)

The estimated resources required for an activity will influence the estimated duration to perform the activity.

(True/False)
4.8/5
(73)

Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.

(Multiple Choice)
4.8/5
(70)

Eliminating negative slack by reducing durations of activities will involve a trade-off in the form of

(Multiple Choice)
4.8/5
(75)

Calculate the earliest start for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.

(Multiple Choice)
5.0/5
(80)

If the planned corrective actions do not result in an acceptable schedule, then

(Multiple Choice)
4.8/5
(64)

The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. What are the ES and EF times for Task B now that Task A is complete?

(Multiple Choice)
4.8/5
(100)

Earliest start time (ES) is the earliest time at which a specific activity can begin

(Multiple Choice)
4.8/5
(63)

If the total slack is zero, the activities on the path do not need to be accelerated but cannot be delayed.

(True/False)
4.9/5
(72)

The ES and EF times are determined by calculating forward-that is, by

(Multiple Choice)
4.8/5
(82)

Schedule control involves four steps. Place these steps in their proper order by stating the letter sequence of their proper order.

(Multiple Choice)
4.8/5
(91)

Negative slack indicates a lack of slack over the entire project and the amount of time

(Multiple Choice)
4.8/5
(78)

In order to establish a basis from which to calculate a schedule using the estimated durations for the activities, it is necessary to

(Multiple Choice)
4.9/5
(74)

When estimating the types and quantities of resources required for each specific activity, it is valuable to involve a person who

(Multiple Choice)
4.8/5
(61)

The amount of slack should determine the priority with which these concentrated efforts are applied.

(True/False)
4.9/5
(76)

The contractor may not want to commit to completing the project by a specific date until the customer has approved the contract.

(True/False)
4.8/5
(86)

Playing the game of inflating estimated durations in anticipation of the project manager negotiating shorter durations is a good practice.

(True/False)
4.8/5
(69)
Showing 21 - 40 of 79
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)