Exam 5: Product and Service Costing: Job-Order System
Exam 1: Introduction to Cost Management115 Questions
Exam 2: Basic Cost Management Concepts161 Questions
Exam 3: Cost Behavior132 Questions
Exam 4: Activity-Based Costing154 Questions
Exam 5: Product and Service Costing: Job-Order System102 Questions
Exam 6: Process Costing137 Questions
Exam 7: Allocating Costs of Support Departments and Joint Products143 Questions
Exam 8: Budgeting for Planning and Control167 Questions
Exam 9: Standard Costing: a Functional-Based Control Approach86 Questions
Exam 10: Decentralization: Responsibility Accounting, Performance Evaluation, and Transfer Pricing110 Questions
Exam 11: Strategic Cost Management121 Questions
Exam 12: Activity-Based Management116 Questions
Exam 13: The Balanced Scorecard: Strategic-Based Control92 Questions
Exam 14: Quality and Environmental Cost Management157 Questions
Exam 15: Lean Accounting and Productivity Measurement137 Questions
Exam 16: Cost-Volume-Profit Analysis108 Questions
Exam 17: Activity Resource Usage Model and Tactical Decision Making98 Questions
Exam 18: Pricing and Profitability Analysis102 Questions
Exam 19: Capital Investment97 Questions
Exam 20: Inventory Management: Economic Order Quantity, Jit, and the Theory of Constraints98 Questions
Select questions type
If there is a debit balance in overhead control, that implies
Free
(Multiple Choice)
4.8/5
(82)
Correct Answer:
A
An actual overhead rate can be calculated
Free
(Multiple Choice)
4.8/5
(75)
Correct Answer:
B
Figure 5-9 Alpha Company manufactures customized motors on a job-order basis.Job 492 is an order for 100 units.It requires the following:
Direct materials $3,000
Direct labor ($10/hr) 1,000
Overhead (150% DL$) 1,500
After inspection, 2 units required rework which required 8 additional direct labor hours and $60 of materials.
-
Refer to Figure 5-9.If the rework is considered normal spoilage, what is the journal entry for overhead control?
Free
(Multiple Choice)
4.7/5
(68)
Correct Answer:
A
Figure 5-7 The following information is available pertaining to the Production Division:
-Refer to Figure 5-7.Based on departmental overhead rates, what is the cost of Job 4X5? Departmental overhead notes for the Mixing Department are based on direct labor hours, while departmental overhead rates for the Finishing Department are based on machine hours.
(Multiple Choice)
4.8/5
(71)
_______________ is the maximum output that can be realized if everything operates efficiently.
(Multiple Choice)
4.8/5
(82)
Figure 5 - 8 Griswold Corporation is a job order costing company that uses activity-based costing to apply overhead to jobs.The following overhead activities were budgeted for the year.
The following information about the jobs was given for September.
By September 30, Jobs 102 and 103 were completed and sold.The remaining jobs were still in process.
-
Refer to Figure 5-8.What is the cost of job 102?
(Multiple Choice)
4.9/5
(77)
Figure 5-5 Wright Corporation had the following information available for December 2011:
Factory overhead rate is 150 percent of direct labor costs.
Job cost sheets had the following balances:
Jobs Z3 and Z4 were not completed at the end of December.
-
Refer to Figure 5-5.What is the cost of goods finished during December for Wright Corporation?
(Multiple Choice)
4.7/5
(91)
What is the most important factor that causes service firms to generally rank lower in customer satisfaction than manufacturing firms?
(Essay)
4.7/5
(95)
_______________ is the association of production costs with the units produced.
(Multiple Choice)
4.9/5
(83)
The _______________ serves as the document that identifies each job and accumulates its manufacturing costs.
(Multiple Choice)
4.9/5
(84)
Figure 5 - 2 The Kraig Corporation manufactures custom-made purses.The following data pertains to Job XY5:
Factory overhead is applied using a plant-wide rate based on direct labor hours.Factory overhead was budgeted at $60,000 for the year and the direct labor hours were estimated to be 15,000.Job XY5 consists of 50 units.
-
Refer to Figure 5-2.What is the labor cost per unit for Job XY5?
(Multiple Choice)
4.9/5
(68)
Explain why actual costing systems are rarely used in practice.
Actual costing systems are rarely used in practice because they do not provide accurate unit cost information on a timely basis.Actual per-unit overhead costs can vary dramatically from period to period because (1) actual costs vary from period to period and/or (2) the number of units produced may vary from period to period.Thus, when actual costing is used, a unit produced during a low-volume month may be assigned a higher cost than a unit produced during a high-volume month, even though the units are identical.
(Essay)
4.7/5
(90)
Figure 5 - 6 In the Mains Company, the following Job cards were totaled at the end of the month:
Job 243 $5,750
Job 244 $4,980
Job 245 $3,675
Job 246 $4,250
Job 247 $5,100
Job 248 $3,800
Jobs 243 and 244 were in Finished Goods Inventory at the beginning of the month.Jobs 245 and 246 were in Work-in-process at the beginning of the month.Jobs 247 and 248 were started during the month.At the end of the month, Jobs 243 and 247 were sent to customers; jobs 245, 247, and 248 were completed and sent to finished goods.
-
Refer to Figure 5-6.What is the cost of goods manufactured for the month?
(Multiple Choice)
4.9/5
(86)
Figure 5 - 8 Griswold Corporation is a job order costing company that uses activity-based costing to apply overhead to jobs.The following overhead activities were budgeted for the year.
The following information about the jobs was given for September.
By September 30, Jobs 102 and 103 were completed and sold.The remaining jobs were still in process.
-
Refer to Figure 5-8.The cost of goods sold would consist of the costs of what jobs?
(Multiple Choice)
4.8/5
(76)
Figure 5-9 Alpha Company manufactures customized motors on a job-order basis.Job 492 is an order for 100 units.It requires the following:
Direct materials $3,000
Direct labor ($10/hr) 1,000
Overhead (150% DL$) 1,500
After inspection, 2 units required rework which required 8 additional direct labor hours and $60 of materials.
-
Refer to Figure 5-9.If the rework is considered abnormal spoilage, what is the cost of job 492?
(Multiple Choice)
4.8/5
(73)
Which of the following costs is usually NOT easily traceable to finished units of product?
(Multiple Choice)
4.9/5
(88)