The difference between projects that fail and those that are ultimately successful has to do with:

(Multiple Choice)
4.9/5
(81)

The mouse executive board meeting was drawing to a conclusion; the only way they would be able to detect the presence of the cat was to tie a bell around its tail.Under their risk management identification scheme,this would fall under:

(Multiple Choice)
4.8/5
(86)

The project team toiled long into the night to develop consequence of failure scores and probability of failure scores as indicated below.What is the overall risk factor for the project? Maturity 0.7 Cost 0.4 Complexity 0.6 Schedule 0.6 Dependency 0.8 Reliability 0.8 Performance 0.9

(Multiple Choice)
4.8/5
(83)

The overall project risk factor is known to be 0.6.The probability of dependency failure is twice the probability of complexity failure and four times the probability of maturity failure.The consequence of performance failure is twice the consequence of reliability failure,four times the consequence of schedule failure and eight times the consequence of cost failure.What is the probability of maturity failure? Maturity Cost Complexity 2 Schedule 2 Dependency 4 Reliability 4 Performance 8

(Multiple Choice)
5.0/5
(81)

The construction foreman posted a large sign requiring all work site visitors to don a hard hat and safety glasses.He also purchased copious quantities of both items and made them readily available at the entrance.The foreman is engaged in:

(Multiple Choice)
4.8/5
(71)

The consequences of failure categories of cost,schedule,reliability,and performance were believed to be 0.25,0.35,0.45,and 0.55.What is the overall consequence of failure?

(Multiple Choice)
4.9/5
(72)

Every one of the nine phases of the PRAM methodology has a deliverable.

(True/False)
4.7/5
(92)

Risk and opportunity:

(Multiple Choice)
4.9/5
(76)

Sketch a flow chart for the PRAM methodology for risk management and briefly describe each step.

(Essay)
5.0/5
(72)

What are fixed-price contracts and liquidated damages? Which party to the contract bears the burden?

(Essay)
4.8/5
(76)

Fred Knievel took out a substantial life insurance policy before he began his trek across North America in his Volvo.Doing so enabled him to:

(Multiple Choice)
4.8/5
(80)

With a cost factor of 0.8,a schedule rating of 0.6,a reliability rating of 0.5,and a performance rating of 0.6,the overall consequence of failure was:

(Multiple Choice)
4.8/5
(74)

The risk is highest in the earliest phase of the project life cycle.

(True/False)
5.0/5
(92)

To protect his poultry from meteorites,the gentleman farmer made hard hats for each bird and installed a meteor detection system that opened umbrellas throughout the yard if a meteor were detected.The safety of his flock thus assured,the farmer was surprised when he read his latest issue of Risk Management Magazine and discovered that this event was:

(Multiple Choice)
4.8/5
(71)

The terpsichorean was familiar with the risks associated with various moves,the accountant knew financial risks forwards and backwards,while the civil engineer could quantify the risks associated with distributed loads on the temporary stage.Their input was used as part of:

(Multiple Choice)
4.8/5
(83)

The probability that the investments made to fund the front-end activities will be lost due to project abandonment is financing risk.

(True/False)
4.8/5
(69)

What does change management accomplish and what are the components of an effective change management program?

(Essay)
4.9/5
(90)

Opportunity emerges from favorable project circumstances and risk from unfavorable events.

(True/False)
4.8/5
(79)

Project penalty clauses that initiate at mutually agreed-on points in the project's development and implementation are:

(Multiple Choice)
4.8/5
(86)

The PostHoc Company specializes in justifying decisions that have already been made.One day they fielded a request to perform a project risk analysis and compute the risk factor for buying an investment property on St.Charles Street in the Big Easy.There was no time (and no need to be perfectly honest)to gather any data regarding the situation; all they had to do was provide an equation and a number that showed the project wasn't too risky for the investor that had already made a decision to proceed.The investor wanted the overall project risk factor to come in at an even 0.5 and also wanted all of the scores for the seven factors that make up this score to have identical values.What is the probability of failure for complexity if these two criteria are met?

(Essay)
4.7/5
(97)