Exam 23: Flexible Budgets and Standard Cost Systems
Exam 1: Accounting and the Business Environment246 Questions
Exam 2: Recording Business Transactions219 Questions
Exam 3: The Adjusting Process225 Questions
Exam 4: Completing the Accounting Cycle208 Questions
Exam 5: Merchandising Operations277 Questions
Exam 6: Merchandise Inventory199 Questions
Exam 7: Accounting Information Systems164 Questions
Exam 8: Internal Control and Cash258 Questions
Exam 9: Receivables233 Questions
Exam 10: Plant Assets,natural Resources,and Intangibles212 Questions
Exam 11: Current Liabilities and Payroll221 Questions
Exam 12: Partnerships171 Questions
Exam 13: Corporations277 Questions
Exam 14: Long-Term Liabilities207 Questions
Exam 15: Investments193 Questions
Exam 16: The Statement of Cash Flows183 Questions
Exam 17: Financial Statement Analysis161 Questions
Exam 18: Introduction to Managerial Accounting245 Questions
Exam 19: Job Order Costing191 Questions
Exam 20: Process Costing173 Questions
Exam 21: Cost-Volume-Profit Analysis295 Questions
Exam 22: Master Budgets181 Questions
Exam 23: Flexible Budgets and Standard Cost Systems223 Questions
Exam 24: Cost Allocation and Responsibility Accounting257 Questions
Exam 25: Short-Term Business Decisions200 Questions
Exam 26: Capital Investment Decisions152 Questions
Select questions type
When using management by exception,which of the following variances would not affect the production manager?
(Multiple Choice)
4.9/5
(64)
A favorable variance has a debit balance and is a contra revenue.
(True/False)
4.8/5
(74)
The management of Guardian Fire Alarms has calculated the following variances: Direct materials cost variance \ 9000 Direct materials efficiency variance 36,000 Direct labor cost variance 15,000 Direct labor efficiency variance 13,500 Total variable overhead variance 8500 Total fixed overhead variance 3000 What is the total direct materials variance of the company?
(Multiple Choice)
4.7/5
(82)
The following information relates to Thomas Manufacturing's overhead costs for the month:
Static budget variable overhead \ 14,200 Static budget fixed overhead \ 5,600 Static budget direct labor hours 1,000 hours Static budget number of units 5,000 units Thomas allocates manufacturing overhead to production based on standard direct labor hours.
Thomas reported the following actual results for last month: actual variable overhead,$14,500; actual fixed overhead,$5,400; actual production of 4,700 units at 0.22 direct labor hours per unit.The standard direct labor time is 0.20 direct labor hours per unit.
Compute the fixed overhead volume variance.
(Essay)
4.7/5
(85)
The fixed overhead volume variance reveals underallocated fixed overhead costs.
(True/False)
4.9/5
(83)
Which of the following will result in an unfavorable direct materials efficiency variance?
(Multiple Choice)
4.7/5
(74)
Midnight Sun Outfitters projected sales of 76,000 units for the year at a unit sales price of $12.00.Actual sales for the year were 72,000 units at $15.00 per unit.Variable costs were budgeted at $4.50 per unit,and the actual variable cost was $4.75 per unit.Budgeted fixed costs totaled $378,000,while actual fixed costs amounted to $410,000.What is the sales volume variance for operating income?
(Multiple Choice)
4.8/5
(90)
Allen Boating Company manufactures special metallic materials and decorative fittings for luxury yachts that require highly skilled labor.Allen uses standard costs to prepare its flexible budget.For the first quarter of the year,direct materials and direct labor standards for one of their popular products were as follows: Direct materials: 1 pound per unit; $11 per pound
Direct labor: 4 hours per unit; $19 per hour
Allen produced 4000 units during the quarter.At the end of the quarter,an examination of the direct materials records showed that the company used 7500 pounds of direct materials and actual total materials costs were $99,300.
What is the direct materials efficiency variance?
(Multiple Choice)
4.9/5
(80)
Which of the following is the correct formula for measuring an efficiency variance?
(Multiple Choice)
4.9/5
(64)
A new factory manager was hired for a company that was experiencing slow production rates and lower production volumes than demanded by management.Upon investigation,the manager found that the workers were poorly motivated and not closely supervised.Midway through the quarter,an incentive program was initiated,and cash bonuses were given when workers hit their production targets.Within a short time,production output increased,but the bonuses had to be charged to the direct labor budget.This could produce a(n)________.
(Multiple Choice)
4.9/5
(82)
Porter Company uses standard costs for its manufacturing division.Standards specify 0.1 direct labor hours per unit of product.The allocation base for variable overhead costs is direct labor hours.At the beginning of the year,the static budget for variable overhead costs included the following data: Production volume 6000 units Budgeted variable overhead costs \ 14,000 Budgeted direct labor hours (DLHr) 600 hours At the end of the year,actual data were as follows:
Production volume 4000 units Actual variable overhead costs \ 15,200 Actual direct labor hours (DLHr) 480 hours What is the variable overhead efficiency variance? (Round any intermediate calculations to the nearest cent,and your final answer to the nearest dollar.)
(Multiple Choice)
4.8/5
(80)
Match the variance to the correct definition.
-Cost variance
(Multiple Choice)
4.7/5
(89)
List three ways in which using a standard cost system helps managers.
(Essay)
4.9/5
(94)
Benson Company manufactures special metallic materials for luxury homes that require highly skilled labor.Benson uses standard costs to prepare its flexible budget.For the first quarter of the year,direct materials and direct labor standards for one of their popular products were as follows: Direct materials: 2 pounds per unit; $3 per pound
Direct labor: 5 hours per unit; $16 per hour
Benson produced 4000 units during the quarter.At the end of the quarter,an examination of the labor costs records showed that the company used 25,000 direct labor hours and actual total direct labor costs were $250,000.What is the direct labor efficiency variance?
(Multiple Choice)
4.9/5
(64)
The variable overhead cost variance measures how well the business ________.
(Multiple Choice)
5.0/5
(84)
Only substantial unfavorable variances should be investigated to determine their causes.
(True/False)
4.9/5
(72)
Devon Company has collected the following data for one of its products: irect materials standard (3 pounds @\ 1/ .) \ 3 per unit Direct materials flexible budget variance - unfavorable \ 15,500 Actual direct materials used 101,000 pounds Actual units produced 18,000 units What is the direct materials efficiency variance?
(Multiple Choice)
4.9/5
(82)
Define variance.What is the difference between a favorable and an unfavorable variance?
(Essay)
5.0/5
(89)
A company is setting its direct materials and direct labor standards for its leading product.Direct materials cost from the supplier are $9 per square foot,net of purchase discount.Freight-in amounts to $0.40 per square foot.Basic wages of the assembly line personnel are $14 per hour.Payroll taxes are approximately 21% of wages.Benefits amount to $2 per hour.How much is the direct materials cost standard per square foot?
(Multiple Choice)
4.9/5
(86)
Showing 41 - 60 of 223
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)