Exam 6: Developing a Project Plan

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

When completing a forward pass you carry the early finish to the next activity where it becomes its early start,unless the next succeeding activity is a merge activity.In this case you select the largest early finish number of all its immediate predecessor activities.Why do you select the largest early finish number?

(Not Answered)
This question doesn't have any answer yet
Ask our community

In developing a project network,neither looping nor conditional statements are permitted.

(True/False)
4.9/5
(93)

In a project network,recycling through a set of activities or __________ is not permitted.

(Short Answer)
4.7/5
(76)

On a project network,the activity times are derived from the

(Multiple Choice)
4.8/5
(76)

If the project has a duration of 13 days,the project should be completed 13 days from the day it starts.

(True/False)
4.8/5
(94)

The critical path in a project network is the

(Multiple Choice)
4.9/5
(85)

The minimum amount of time a dependent activity must be delayed to begin or end is referred to as

(Multiple Choice)
5.0/5
(70)

What is a hammock activity and give an example?

(Not Answered)
This question doesn't have any answer yet
Ask our community

The assumption that all immediate preceding activities must be 100% complete is too restrictive in some situations.When an activity is broken down into smaller segments in order to start the succeeding activity sooner,this is called

(Multiple Choice)
4.9/5
(81)

An element in the project that consumes time is a(n)___________.

(Short Answer)
4.8/5
(98)

A(n)_____________ calculates project duration.

(Short Answer)
4.9/5
(79)

If testing cannot be completed any earlier than four days after the prototype has been built,what type of lag exists?

(Multiple Choice)
4.9/5
(69)

Burst activities have more than one activity immediately following them (more than one dependency arrow flowing from them).

(True/False)
4.9/5
(79)

Activities which can take place at the same time are termed

(Multiple Choice)
4.9/5
(87)

Bill is building a project network that involves testing a prototype.He must design the prototype (activity 1),build the prototype (activity 2),and test the prototype (activity 3).Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3.If the prototype fails testing,Bill must redesign the prototype;therefore,activity 3 is a predecessor for activity 1.This is an example of

(Multiple Choice)
4.8/5
(83)

Experience suggests that when there are multiple starts,a common start node should be used to indicate a clear project beginning on the network.Similarly,a single project end node can be used to indicate a clear ending.

(True/False)
4.9/5
(79)

Activities that can occur while an activity is taking place are called ________ activities.

(Short Answer)
4.8/5
(77)

When an activity with a long duration is broken into smaller segments so that the following activities can begin sooner it is called __________.

(Short Answer)
4.9/5
(87)

What is a lag and give an example of when you would need to use one?

(Not Answered)
This question doesn't have any answer yet
Ask our community

The WBS identifies dependencies,the sequencing of activities,and the timing of activities.

(True/False)
4.9/5
(74)
Showing 21 - 40 of 94