Exam 7: Managing Risk
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection87 Questions
Exam 3: Organization: Structure and Culture90 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk86 Questions
Exam 8: Scheduling Resources and Costs91 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects95 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management86 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
The ________ form identifies each risk event,the likelihood of it occurring,the potential impact,when it may occur,and the degree of difficulty in detecting it.
(Short Answer)
5.0/5
(62)
A ____________ is an alternative that will be used if a possible foreseen risk event becomes a reality.
(Short Answer)
4.8/5
(77)
Contingency funding is made up of budget reserves and management reserves.
(True/False)
4.9/5
(66)
Tools such as a risk assessment form and a risk severity matrix are used to
(Multiple Choice)
4.9/5
(74)
If,during risk response development,you successfully identify how you will respond to a risk,contingency planning is unnecessary.
(True/False)
4.7/5
(75)
Performance bonds,warranties,and insurance are examples of ________ a risk.
(Short Answer)
4.9/5
(79)
Budget reserves are set up to cover identified risks associated with specific segments of a project while management reserves are set up to cover unidentified risks associated with the total project.
(True/False)
5.0/5
(89)
________ reserves are identified for specific work packages and are distributed by the project manager and the team members.
(Short Answer)
4.7/5
(81)
Choosing to move a concert indoors to eliminate the threat of bad weather is an example of ____________ a risk.
(Short Answer)
4.9/5
(82)
Risk events that occur in the early stages of a project will have a greater cost impact than those that occur in later stages.
(True/False)
4.9/5
(68)
While a "can do" attitude is essential during implementation,project managers have to encourage critical thinking when it comes to risk identification.
(True/False)
4.7/5
(81)
What is the difference between mitigating a risk and a contingency plan? Provide real life examples that illustrate the difference.
(Not Answered)
This question doesn't have any answer yet
Describe the relationship between the likelihood of a risk event occurring and the cost of fixing the risk event as a project proceeds through its life cycle.
(Not Answered)
This question doesn't have any answer yet
The probability that a risk event will occur is higher during the initial stages of a project.
(True/False)
4.9/5
(71)
What is a "trigger" and why is it important when planning contingencies?
(Not Answered)
This question doesn't have any answer yet
Why might an organization be opposed to developing and implementing a thorough risk management process?
(Not Answered)
This question doesn't have any answer yet
The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as
(Multiple Choice)
4.8/5
(91)
A list of questions that address traditional areas of uncertainty on a project is known as a _________.
(Short Answer)
4.7/5
(81)
_______________ focuses on how to respond to events that have a positive impact on a project.
(Multiple Choice)
4.9/5
(85)
Fixed-price contracts are an example of transferring risk from an owner to a contractor.
(True/False)
4.8/5
(85)
Showing 21 - 40 of 86
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)