The easiest and most commonly used technique for analyzing risks is ________.

(Short Answer)
4.8/5
(74)

Which of the following is used to review activity and project risk?

(Multiple Choice)
4.9/5
(74)

In a Risk Severity Matrix a green zone risk is considered inconsequential and ignored unless their status changes.

(True/False)
4.8/5
(93)

A ____________ is useful for summarizing how the project team plans to manage risks that have been identified.

(Short Answer)
4.9/5
(84)

The first step in the risk management process is Risk Assessment.

(True/False)
4.8/5
(87)

A Risk Response Matrix contains all of the following except

(Multiple Choice)
4.8/5
(86)

Which of the following is not one of the potential responses to a specific risk event?

(Multiple Choice)
4.8/5
(77)

The two scales of a risk severity matrix measure

(Multiple Choice)
4.8/5
(63)

If a risk event is very unlikely to occur the project owner would probably ________ the risk.

(Short Answer)
4.8/5
(78)

When the entertainment industry formed a consortium to define a common operating format for DVD it was ________ the risk.

(Short Answer)
4.9/5
(81)

Budget reserves are setup to cover identified risks associated with specific segments of a project while management reserves are set up to cover unidentified risks associated with the total project.

(True/False)
4.8/5
(83)

Fixed price contracts are an example of transferring risk from an owner to a contractor.

(True/False)
4.9/5
(81)

Funds that are for identified risks that have a low probability of occurring and that decrease as the project progresses are called ______ reserves.

(Multiple Choice)
4.7/5
(87)

Project managers need to establish an environment in which participants feel comfortable raising concerns and admitting mistakes.

(True/False)
4.8/5
(83)

One common mistake that is made early on in the risk identification process is to focus on consequences and not on the events that could produce consequences.

(True/False)
4.8/5
(87)

Identify and briefly describe the five ways to respond to identified risks.

(Essay)
4.8/5
(73)

Change management systems involve reporting, controlling, and recording changes to the project baseline.

(True/False)
4.8/5
(70)

A ________ identifies what to do if a potential risk event actually occurs.

(Short Answer)
4.9/5
(83)

The risk associated with one of the key members being stuck by lightning would most likely be handled by which of the following?

(Multiple Choice)
4.7/5
(73)

The demolition of the Seattle Kingdome (Snapshot from Practice) is an example of which of the following?

(Multiple Choice)
4.8/5
(69)