Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture105 Questions
Exam 3: Project Selection and Portfolio Management103 Questions
Exam 4: Leadership and the Project Manager112 Questions
Exam 5: Scope Management111 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting105 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain105 Questions
Exam 12: Resource Management98 Questions
Exam 13: Project Evaluation and Control107 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
How might a project manager alter a straightforward PERT network to accommodate an inordinately large and complex project?
(Essay)
4.8/5
(82)
Consider the project described by the table where all durations are in days and the costs in dollars.What is the minimum cost of completing this project in 150 days?
Normal Minimum Normal Activity Predecessor Time Time Cost Crash Cost 15 12 800 1,100 30 22 2,500 4,100 45 37 21,000 33,000 20 17 15,000 22,000 5 4 3,000 3,300 10 7 13,000 15,500 30 25 41,000 46,000 , 50 45 30,000 37,500 25 20 20,000 25,000 35 33 6,500 7,200 40 33 16,500 19,400 15 13 14,400 18,600 30 26 23,500 27,500 20 15 15,250 23,500 , 5 5 5,000 5,000
(Essay)
4.9/5
(85)
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $4,000 per week for every week the project exceeds 37 weeks.What is the lowest total cost for completing this project? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 \ 12,000 5 \ 22,000 A 12 \ 18,000 9 \ 32,000 C A 15 \ 22,000 9 \ 62,000 3 \ 9,000 2 \ 18,000 C 9 \ 15,000 5 \ 35,000 7 \ 5,000 5 \ 8,000 8 \ 13,000 6 \ 23,000 12 \ 20,000 8 \ 32,000 6 \ 45,000 4 \ 56,000
(Multiple Choice)
4.9/5
(77)
-Use the Gantt chart and activity list to determine which resource is used the least. Activity Resources Activity Resources 5 1 1 4 5 3 2 1 2 2 4 3
(Multiple Choice)
5.0/5
(70)
-Use the Gantt chart and activity list to determine which resource is used the most. Activity Resources Activity Resources 3,5 1,2 1 4 2,5 3 4,1 1 2 3,4 2 3
(Multiple Choice)
4.9/5
(94)
-Use the Gantt chart and activity list to determine which resource has the greatest continual use. Activity Resources Activity Resources 5 1 1 5 5 3 2 1 2 2 4 3
(Multiple Choice)
4.7/5
(62)
-Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest. Activity Resources Activity Resources 3,5 1,2 1 4 2,5 3 4,1 1 2 3,4 2 3
(Multiple Choice)
4.8/5
(75)
What is a Gantt chart,what information does one provide,and what are the benefits of using one?
(Essay)
4.8/5
(68)
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 25 weeks.What is the lowest total cost duration for completing this project? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 \ 12,000 5 \ 22,000 A 12 \ 18,000 9 \ 32,000 C A 15 \ 22,000 9 \ 62,000 3 \ 9,000 2 \ 18,000 C 9 \ 15,000 5 \ 35,000 7 \ 5,000 5 \ 8,000 8 \ 13,000 6 \ 23,000 12 \ 20,000 8 \ 32,000 6 \ 45,000 4 \ 56,000
(Multiple Choice)
4.9/5
(90)
What is the minimum cost completion time for this project if the activities have normal and crash costs as indicated and there is a $1,000 fixed cost for each day on site plus a $500 penalty for each activity that is crashed? The crash costs represent the cost of a fully expedited activity.For example,reducing activity Y from 13 days to 12 days costs an extra $100 on top of the $500 expediting cost for a total cost of $2,600.Reducing Y from 13 days to 10 days costs an extra $300 on top of the $500 expediting cost,for a total activity cost of $2,800.
Normal Normal Crash Activity Predecessor Time Cost Time Crash Cost 2 \ 2,000 2 \ 2,000 13 \ 2,000 10 \ 2,300 19 \ 2,000 15 \ 3,000 18 \ 2,000 15 \ 3,000 10 \ 2,000 9 \ 3,000 13 \ 2,000 11 \ 3,000 18 \ 2,000 14 \ 4,000 4 \ 2,000 3 \ 3,000 6 \ 2,000 5 \ 3,000 , 15 \ 2,000 13 \ 3,000 T 13 \ 2,000 12 \ 3,000 , 4 \ 2,000 4 \ 2,000
(Essay)
4.9/5
(72)