Exam 11: Project Risk Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A ________ presents a hierarchical organization of risks based on categories such as operational,strategic,finance,external,and project management.

(Multiple Choice)
4.9/5
(80)

Which of the following describes the activities appropriately performed by the project team during Perform Qualitative Risk Analysis?​ 

(Multiple Choice)
4.7/5
(89)

All of the following describe an appropriate application of Plan Risk Responses in project management EXCEPT:​ 

(Multiple Choice)
4.8/5
(83)

Which of the following activities illustrates a risk response strategy designed to research a threat or an opportunity? 

(Multiple Choice)
4.8/5
(90)

The process of defining how to conduct risk management activities for a project is known as Project Risk Absorption Methodology (PRAM).

(True/False)
4.9/5
(83)

Which of the following activities illustrates a risk response strategy designed to mitigate a threat? 

(Multiple Choice)
4.9/5
(87)

When complete,the risk register presents the results of both qualitative and quantitative risk analysis as well as risk response planning.

(True/False)
4.7/5
(70)

Once risks have been identified and analyzed,the project team decides how they will handle each risk.

(True/False)
4.9/5
(78)

In Agile projects early risk planning,assessment and response planning is done at a high level,and more detailed and timely risk management occurs during the planning of each subsequent iteration,in daily stand-up meetings,and in retrospectives at the end of each iteration.

(True/False)
4.8/5
(68)

  Figure 10-1 Excerpt from Internet Project Risk Register -Consider the excerpt of the Internet Project risk register presented in Figure 10-1.Which of the following risk events should receive the highest priority for the development of risk responses?​  Figure 10-1 Excerpt from Internet Project Risk Register -Consider the excerpt of the Internet Project risk register presented in Figure 10-1.Which of the following risk events should receive the highest priority for the development of risk responses?​ 

(Multiple Choice)
4.7/5
(68)

Which of the following describes how the team uses a cause-and-effect diagram to support project risk analysis?​ 

(Multiple Choice)
4.9/5
(81)

The purpose of risk management is to eliminate all project risk.

(True/False)
4.8/5
(79)

All of the following activities illustrate a risk response strategy designed to exploit an opportunity EXCEPT: 

(Multiple Choice)
4.8/5
(88)

The cost per risk for risks discovered early in the project is often more than the cost per risk for risks discovered late because there is more opportunity for the risk to impact several dimensions of the project.

(True/False)
4.8/5
(81)

How might you approach the prioritization of the risk events identified by your project team and subject matter experts? How would you use the results of this prioritization effort to guide the development of risk responses?

(Essay)
4.7/5
(85)

Perform Quantitative Risk Analysis is the process of numerically analyzing the effect of identified risks on overall project objectives.

(True/False)
4.9/5
(84)

When a project team elects to purchase insurance,or adopts a fixed price contract with a vendor,or hires an expert,it is demonstrating which of the following risk response strategies? 

(Multiple Choice)
4.7/5
(85)

Risk response strategy decisions should reflect a thorough understanding of the priorities that key stakeholders have for cost,schedule,scope,and quality.

(True/False)
4.9/5
(76)

All of the following methods have proven to be useful techniques to help project teams identify the risks that might impact the project EXCEPT: 

(Multiple Choice)
4.9/5
(72)

All of these describe contemporary methods of risk prioritization in project management EXCEPT: 

(Multiple Choice)
4.8/5
(102)
Showing 21 - 40 of 45