Exam 6: Stakeholder Analysis and Communication Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Describe the approach you would use to build relationships with key external stakeholders.

(Essay)
4.8/5
(76)

Stakeholders can be classified as internal to,or external to the organization.Examples of external stakeholders include government agencies and professional groups.

(True/False)
4.7/5
(79)

A project communications matrix includes all of the following information EXCEPT: 

(Multiple Choice)
4.9/5
(78)

A project manager must use effective communications to set and manage expectations of all stakeholders as well as to ensure that project work is completed properly and on time.

(True/False)
4.9/5
(69)

The communications management plan is finalized during project planning,and should only be changed through a formal change control process.

(True/False)
4.9/5
(81)

In order to plan for a project meeting,project managers should develop an agenda.Which of the statements below is NOT accurate with respect to a project meeting agenda?​ 

(Multiple Choice)
4.8/5
(67)

During the Manage Communications process,project managers must continuously monitor relationships,communications,and lessons learned in order to manage stakeholder expectations.

(True/False)
4.9/5
(80)

In the Plus-Delta method of evaluating project meetings,the "delta" column is used for team members to offer their opinion about one aspect of the meeting that ________.​ 

(Multiple Choice)
4.8/5
(64)

A communications management plan is a repository of information regarding all project stakeholders,and is often in the format of a matrix.

(True/False)
4.8/5
(74)

The primary output of the "Identify Stakeholders" process is the project communications plan.

(True/False)
4.9/5
(80)

By identifying stakeholders and their needs,project managers can be more effective in all the following ways EXCEPT: 

(Multiple Choice)
4.7/5
(87)

A stakeholder engagement matrix documents the engagement levels of project stakeholders,how much they are currently supporting or opposing the project,along with where you would like them to be and strategies you may employ to move them.

(True/False)
4.8/5
(82)

Common purposes for project communications include status reporting and efforts to obtain approval of project outputs.

(True/False)
4.9/5
(75)

Communications to stakeholders are necessary for which of the following reasons? 

(Multiple Choice)
4.9/5
(68)

A situation that requires a decision to be made,but one that the team that cannot make now,usually due to needing more information or time, is called a(n)_____:​ 

(Multiple Choice)
4.7/5
(84)

Which of the following statements accurately describes a communications management plan?​ 

(Multiple Choice)
4.9/5
(75)

Which of these is NOT one of the three methods of communication that will be documented in a communication plan?​ 

(Multiple Choice)
4.8/5
(76)

Project managers should purposefully plan and carry out relationship-building activities with stakeholders that lead to respect and trust.

(True/False)
4.8/5
(80)

During stakeholder analysis,stakeholders can be prioritized based on three factors including "power",which is defined as the time sensitivity and legitimacy of their claim.

(True/False)
4.8/5
(88)

A project communications plan generally includes all of the following information EXCEPT:​ 

(Multiple Choice)
4.9/5
(87)