Damages that compensate the nonbreaching party for the loss of a bargain are known as consecutive damages.

(True/False)
4.9/5
(87)

Cowtown Creamery,Inc.,needs a certain part for its pasteurizing equipment to continue its operations and orders one for $3,000 from Dairy Supplies Company. Cowtown tells Dairy Supplies that it must receive the part by Tuesday or it will lose $10,000. Dairy Supplies ships the part late. Cowtown can recover

(Multiple Choice)
4.7/5
(82)

Nogales Ceramics pays Omar $15,000 to propose an online marketing campaign. Two days later,Omar tells Nogales that he has accepted a job in Silicon Valley and cannot plan the campaign. As compensatory damages,Nogales can recover

(Multiple Choice)
5.0/5
(92)

Sati contracts to work exclusively for Thermal Imaging Company during July for $5,000. On June 30,Thermal Imaging cancels the contract. Sati finds a similar job for the month of July but earns only $3,000. Sati files a suit against Thermal Imaging. As compensatory damages,Sati can recover

(Multiple Choice)
4.9/5
(86)

Dry Gulch Farms hires Elliot to repair its irrigation system on site on a certain date for $2,500,but Elliot does not show up as agreed. Dry Gulch hires Fernando to do the job for $2,000. Dry Gulch may recover from Elliot

(Multiple Choice)
4.9/5
(85)

A party seeking to recover in quasi contract must show that the other party has been unjustly enriched.

(True/False)
4.7/5
(76)

Builders,Inc.,agrees to construct an office building for Champion Fitness Clubs,Inc. The project proceeds according to plan,but before it is done,Champion tells Buildersto quit. Buildersmay recover

(Multiple Choice)
4.8/5
(68)

Ambrose enters into a contract to buy 350 acres from Belle Vista Farms to cultivate grapes and open a winery. -Refer to Fact Pattern 17-1. If Belle Vista breaches the contract,Ambrose's remedy would most likely be

(Multiple Choice)
4.7/5
(89)

Metro Facilities,Inc.,contracts to sell a parking lot to Nouveau Property Company. The contract provides that if Metro does not close the deal by September 15,it must pay Nouveau one-half of the contract price. This provision is not enforceable because it is

(Multiple Choice)
4.9/5
(77)

In a contract for a sale of goods,the usual measure of compensatory damages is the difference between the retail price and the wholesale price.

(True/False)
4.9/5
(81)

Excavate n' Fill,Inc.,enters into a contract with Fred to fill and landscape an abandoned quarry on Fred's land. Fred advances Excavate n' Fill10 percent of its cost. The parties rescind the contract. Excavate n' Fill's refund of the payment is

(Multiple Choice)
4.8/5
(79)

Liquidated damages provisions usually are enforceable.

(True/False)
4.8/5
(85)

Reformation is an equitable remedy that allows a court to rewrite a contract to suit itself.

(True/False)
4.8/5
(89)

A liquidated damages provision specifies that a certain amount is to be paid on a breach of contract when the nonbreaching party elects to receive cash.

(True/False)
4.8/5
(66)

Ambrose enters into a contract to buy 350 acres from Belle Vista Farms to cultivate grapes and open a winery. -Refer to Fact Pattern 17-1. If Ambrose breaches the contract,Belle Vista's remedy would most likely be

(Multiple Choice)
4.8/5
(74)

Porches & Verandas,Inc.,agrees to build a screen porch for Quinn,but fails to complete the job. Quinnhires Ramadas,Inc.,to finish the project. Quinn may recover from Porches & Verandas

(Multiple Choice)
4.8/5
(68)

The most common remedies available to a nonbreaching party include damages,rescission and restitution,and specific performance.

(True/False)
4.7/5
(85)

Ready Repair Service enters into a contract to fix washers and dryers in Scrub n' Dry Company's coin-operated laundries. If Ready Repair breaches the contract,Scrub n' Dry can

(Multiple Choice)
4.7/5
(80)

A contract for a sale of land from Bayside Properties,Inc.,to City Development Corporation contains an erroneous legal description. The most appropriate remedy for these parties is

(Multiple Choice)
4.9/5
(74)

Meatpackers,Inc.,enters into a contract with Nemiah's Ranch for the delivery of a certain number of beef cattle on a set schedule. Nemiah's delays the first delivery for five days,aware that Meatpackers loses a certain percentage of profit each day. An award to Meatpackersof consequential damages would

(Multiple Choice)
4.9/5
(70)
Showing 21 - 40 of 72