Exam 5: Scheduling the Project

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The difference between EST and LFT is called slack.

Free
(True/False)
4.8/5
(79)
Correct Answer:
Verified

False

PERT was originally used for what type of project?

Free
(Multiple Choice)
4.9/5
(79)
Correct Answer:
Verified

C

A disadvantage of Gantt charts is that they are hard to draw.

Free
(True/False)
4.7/5
(91)
Correct Answer:
Verified

False

Which of the following is typically used as the best estimate of task duration?

(Multiple Choice)
4.9/5
(74)

To manage a project successfully,the project manager need only pay close attention to tasks on the critical path.

(True/False)
4.9/5
(71)

The difference between LST and LFT is called slack.

(True/False)
4.9/5
(89)

A Term NOT used in the discussion of PERT/CPM analysis is

(Multiple Choice)
4.9/5
(90)

When it was originally developed,PERT used certain (deterministic)methods to estimate activity duration.

(True/False)
4.9/5
(83)

Another name for total slack is free slack.

(True/False)
4.7/5
(61)

What is a merger and what problems do mergers create?

(True/False)
4.7/5
(97)

The formula for the expected time of an activity in a network assumes that the optimistic,pessimistic,and most likely time estimates have a Beta distribution.

(True/False)
4.8/5
(74)

Technical dependencies on a project plan are easiest to see on a:

(Multiple Choice)
4.7/5
(74)

It is easiest to see lead and lag time in a project task on a PERT/CPM networks.

(True/False)
4.9/5
(88)

The difference between the LST and EST is called slack.

(True/False)
5.0/5
(89)

Standard Pert/CPM networks can be use to resolve probabilistic concerns

(True/False)
4.9/5
(82)

The amount of time a noncritical task can be delayed without delaying the project is called?

(Multiple Choice)
4.8/5
(68)

What is the standard deviation of a task with optimistic,most likely,and pessimistic times of 3,4,and 7 days respectively assuming the estimates were made at the 99% plus level?

(Multiple Choice)
4.7/5
(76)

Critical path tasks always have zero slack.

(True/False)
4.9/5
(79)

Milestones cannot be identified on a Gantt Chart.

(True/False)
4.9/5
(73)

An identifiable state resulting from the completion of one or more activities is called?

(Multiple Choice)
4.7/5
(78)
Showing 1 - 20 of 46