Before starting piling work, a complete knowledge of underground structures (such as sewers, water pipeline, gas mains etc.) is essential.
(Multiple Choice)
4.9/5
(76)
Heavy equipment, such as excavating machinery, trucks, dumpers, etc. should be kept away from the excavated sides at a distance not less than the depth of trench
(Multiple Choice)
4.9/5
(81)
In case of cantilever beam, reinforcement must be placed at the ....... of the member.
(Multiple Choice)
4.8/5
(72)