Exam 5: Software Development and Management Terminology
Exam 1: Project Management Terminology and Concepts23 Questions
Exam 2: Software Development Methodologies and Project Management Techniques23 Questions
Exam 3: Software Development and Project Management25 Questions
Exam 4: Software Development and Design24 Questions
Exam 5: Software Development and Management Terminology22 Questions
Select questions type
. The scope of the deliverables for an increment is rigidly constrained by an agreed deadline called as ____________.
Free
(Multiple Choice)
4.7/5
(80)
Correct Answer:
B
Diagrammatic form for Flow oriented Modelling………
Free
(Multiple Choice)
4.8/5
(85)
Correct Answer:
C
The sub-characteristics of efficiency is …..
Free
(Multiple Choice)
4.9/5
(72)
Correct Answer:
C
. In software prototype, partial working model is classified into ________.
(Multiple Choice)
4.8/5
(88)
Zero duration activities but are assumed to start at the same time as the first and the end at the same time as the last one is called__________ activity.
(Multiple Choice)
4.8/5
(72)
________ a set of attributes (data items) and that will be manipulated within the software (system).
(Multiple Choice)
4.9/5
(83)
In Software Prototype, ___________ means copies of input screens are shown to the users on a workstation, but the screens cannot actually be used.
(Multiple Choice)
4.8/5
(88)
he Cost Benefit Analysis is done for ___________ feasibility.
(Multiple Choice)
4.8/5
(83)
One can_______ is classified into Functional and Non-functional.
(Multiple Choice)
5.0/5
(79)
Security (backups, firewall) will be a ________ requirement.
(Multiple Choice)
4.8/5
(82)
……………..is called if subsequent have the time by which an activity may be delayed without affecting.
(Multiple Choice)
4.8/5
(78)
_________ activities on the network diagram have zero duration and use no resources.
(Multiple Choice)
4.9/5
(89)
The activities have zero duration but are assumed to start at the sametime as the first and the end at the same time as the last one iscalled__________ activity.
(Multiple Choice)
4.9/5
(80)
____ is carried out to calculate the earliest dates on which each activity may be started and completed.
(Multiple Choice)
4.8/5
(85)
Sometimes redesigns of the code is often called as ________.
(Multiple Choice)
4.7/5
(78)
Showing 1 - 20 of 22
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)