Exam 1: Making Economic Decisions
Exam 1: Making Economic Decisions9 Questions
Exam 2: Estimating Engineering Costs and Benefits12 Questions
Exam 3: Interest and Equivalence17 Questions
Exam 4: Equivalence for Repeated Cash Flows22 Questions
Exam 5: Present Worth Analysis16 Questions
Exam 6: Annual Cash Flow Analysis17 Questions
Exam 7: Rate of Return Analysis12 Questions
Exam 8: Choosing the Best Alternative12 Questions
Exam 9: Other Analysis Techniques18 Questions
Exam 10: Uncertainty in Future Events14 Questions
Exam 11: Depreciation16 Questions
Exam 12: Income Taxes for Corporations13 Questions
Exam 13: Replacement Analysis11 Questions
Exam 14: Inflation and Price Change9 Questions
Exam 15: Selection of a Minimum Attractive Rate of Return9 Questions
Exam 16: Economic Analysis in the Public Sector9 Questions
Exam 17: Accounting and Engineering Economy8 Questions
Select questions type
Case Study 1
Ross Manufacturing in Atlanta is considering outsourcing a component from an offshore company. The company has collected the following data to make an economic decision.
Cost to make it in-house = $96 per unit.
Annual Demand = 500,000 units
Price quoted by the Asian company = $90 per unit plus a shipping cost of $20,000 per shipment.
-Determine the number of shipments per year that the company can require the supplier to make in order to justify outsourcing.
Free
(Short Answer)
4.9/5
(78)
Correct Answer:
150
In decision making related to engineering projects, based on economics, the most important non-economic factor is:
_
Free
(Multiple Choice)
4.9/5
(92)
Correct Answer:
C
Case Study 1
Ross Manufacturing in Atlanta is considering outsourcing a component from an offshore company. The company has collected the following data to make an economic decision.
Cost to make it in-house = $96 per unit.
Annual Demand = 500,000 units
Price quoted by the Asian company = $90 per unit plus a shipping cost of $20,000 per shipment.
-In addition to cost consideration, what other factors would weigh in decision making?
Free
(Essay)
4.8/5
(80)
Correct Answer:
Reputation of overseas vendor, quality of parts, political climate of the country in which the vendor is from, labor regulations.
In engineering economic cost is a decision making tangible factor.
(True/False)
4.7/5
(63)
Most engineering projects that have economic consequences have to be justified using economic decision making methods.
(True/False)
4.8/5
(85)
Jim Watts, a senior engineer at a major global company, has been working in a foreign country all of 2016. He was paid in local currency, FC. One FC = 0.3$. The currency fluctuation in 2016 for each of the four quarters was 6.2, 6.9, 4.2, and 3.8. This contracted salary for the year was that he would be paid 75,000 in FC per quarter. What was his earnings in $ for 2016?
(Short Answer)
4.7/5
(85)
An example for fixed input in economic decision making is that the project manager has a budget of one million dollars for this project.
(True/False)
4.9/5
(83)
Decision making in engineering economy is concerned with choosing the best __________.
(Multiple Choice)
4.8/5
(74)
In an economic decision making, when the inputs and outputs are fixed, the criterion to use is minimize the input.