Exam 7: Killer Clauses
Exam 1: Getting Started18 Questions
Exam 2: An Introduction to Contracts, Torts, Statutes and Regulations22 Questions
Exam 3: Owners, Designers, and Constructors20 Questions
Exam 4: The Basics of Construction Contracts24 Questions
Exam 5: Different Construction Contract Delivery Methods23 Questions
Exam 6: Interpreting the Contract38 Questions
Exam 7: Killer Clauses26 Questions
Exam 8: Insurance23 Questions
Exam 9: Bonds17 Questions
Exam 10: Warranties11 Questions
Exam 11: Getting Started20 Questions
Exam 12: Differing Site Conditions14 Questions
Exam 13: Schedule21 Questions
Exam 14: Liens12 Questions
Select questions type
Generally not included in a Time and Material cost is
Free
(Multiple Choice)
4.8/5
(87)
Correct Answer:
A
An exculpatory clause shifts responsibility for actions done or caused by one party to another party
Free
(True/False)
4.9/5
(91)
Correct Answer:
True
The contract will usually clearly define what will be included in Time and Material costs
(True/False)
4.8/5
(65)
If there is a ""no damage for delay clause"" the Contract Administrator
(Multiple Choice)
4.9/5
(87)
Whether there is a ""notice clause"" or not in the contract, the Contract Administrator should notify the owner of any delays
(True/False)
4.9/5
(92)
Contracts can contain indemnity clauses requiring another party to assume the costs for damages done by another party
(True/False)
4.9/5
(79)
An Owner cannot delay the whole or a portion of the work without compensating the Constructor
(True/False)
4.7/5
(80)
In the event of bankruptcy of a Supplier, materials stored at the Supplier's facility become the property of the Contractor
(True/False)
4.9/5
(75)
For progress billing, the Contract Administrator should coordinate with
(Multiple Choice)
4.8/5
(73)
A PRP does not have to be the party or entity that installed the hazardous material
(True/False)
4.9/5
(77)
When an Owner exercises a ""Termination for Convenience"" the Constructor is not entitled to any further compensation
(True/False)
5.0/5
(79)
Contractors should be alert to hazardous substances in buildings
(Multiple Choice)
4.8/5
(67)
Acceleration clauses cannot require a Constructor to perform work in a manner that is more costly than originally planned
(True/False)
4.9/5
(87)
Showing 1 - 20 of 26
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)