Exam 7: Killer Clauses

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Generally not included in a Time and Material cost is

Free
(Multiple Choice)
4.8/5
(87)
Correct Answer:
Verified

A

An exculpatory clause shifts responsibility for actions done or caused by one party to another party

Free
(True/False)
4.9/5
(91)
Correct Answer:
Verified

True

When terminating for cause

Free
(Multiple Choice)
4.8/5
(76)
Correct Answer:
Verified

A

The contract will usually clearly define what will be included in Time and Material costs

(True/False)
4.8/5
(65)

If there is a ""no damage for delay clause"" the Contract Administrator

(Multiple Choice)
4.9/5
(87)

Whether there is a ""notice clause"" or not in the contract, the Contract Administrator should notify the owner of any delays

(True/False)
4.9/5
(92)

Indemnity clauses

(Multiple Choice)
4.9/5
(78)

Exculpatory clauses

(Multiple Choice)
4.8/5
(85)

Contracts can contain indemnity clauses requiring another party to assume the costs for damages done by another party

(True/False)
4.9/5
(79)

An Owner cannot delay the whole or a portion of the work without compensating the Constructor

(True/False)
4.7/5
(80)

In the event of bankruptcy of a Supplier, materials stored at the Supplier's facility become the property of the Contractor

(True/False)
4.9/5
(75)

For progress billing, the Contract Administrator should coordinate with

(Multiple Choice)
4.8/5
(73)

A PRP does not have to be the party or entity that installed the hazardous material

(True/False)
4.9/5
(77)

When an Owner exercises a ""Termination for Convenience"" the Constructor is not entitled to any further compensation

(True/False)
5.0/5
(79)

Contractors should be alert to hazardous substances in buildings

(Multiple Choice)
4.8/5
(67)

If a hazardous substance is exposed

(Multiple Choice)
4.8/5
(82)

A Mechanics Lien is

(Multiple Choice)
4.8/5
(85)

An Acceleration clause is illegal

(True/False)
5.0/5
(88)

Acceleration clauses cannot require a Constructor to perform work in a manner that is more costly than originally planned

(True/False)
4.9/5
(87)

A Constructor cannot be held responsible for hidden conditions

(True/False)
4.8/5
(77)
Showing 1 - 20 of 26