Exam 35: Renovations, Remodeling, and Additions
Exam 1: Professional Architectural Careers15 Questions
Exam 2: Exploring Residential Design and Professional Office Practice15 Questions
Exam 3: Preparing for Success15 Questions
Exam 4: Computer-Aided Design in Architecture15 Questions
Exam 5: Guidelines and Codes That Affect Design15 Questions
Exam 6: Interior Design Considerations15 Questions
Exam 7: Exterior Design Factors and Styles15 Questions
Exam 8: Environmental Design Considerations15 Questions
Exam 9: Land Descriptions and Drawings15 Questions
Exam 10: Site-Related Drawing Layout15 Questions
Exam 11: Floor Plans - Symbols, Annotation, and Dimensions15 Questions
Exam 12: Completing a Floor Plan With Cad15 Questions
Exam 13: Electrical Plans15 Questions
Exam 14: Plumbing Systems15 Questions
Exam 15: Comfort Control Systems15 Questions
Exam 16: Roof Plan Components15 Questions
Exam 17: Roof Plan Layout With Cad15 Questions
Exam 18: Introduction to Elevations15 Questions
Exam 19: Elevation Layout and Cad Drawing Techniques15 Questions
Exam 20: Representing Interior Finishing Materials and Cabinets With Cad15 Questions
Exam 21: Framing Methods15 Questions
Exam 22: Structural Components15 Questions
Exam 23: Design Criteria for Structural Loading15 Questions
Exam 24: Sizing Joists, Rafters, and Beams15 Questions
Exam 25: Drawing Framing Plans15 Questions
Exam 26: Foundation Systems15 Questions
Exam 27: Floor Systems and Foundation Support15 Questions
Exam 28: Foundation Plan Layout15 Questions
Exam 29: Sectioning Basics15 Questions
Exam 30: Section Layout15 Questions
Exam 31: Stair Construction and Layout15 Questions
Exam 32: Fireplace Construction and Layout15 Questions
Exam 33: Construction Documentation, Specifications, and Project Manuals15 Questions
Exam 34: Presentation Drawings15 Questions
Exam 35: Renovations, Remodeling, and Additions15 Questions
Select questions type
When completing the elevations, items on the ELEV NEWW layer should be drawn with _____.
Free
(Multiple Choice)
4.7/5
(80)
Correct Answer:
A
When the floor plan is complete, ____ and notes should clearly define all new materials.
Free
(Multiple Choice)
4.8/5
(96)
Correct Answer:
D
A(n) ____ permit may be required for storm water disposal.
Free
(Multiple Choice)
4.8/5
(83)
Correct Answer:
B
The ____ will provide the size of the proposed job site and help you to determine the property lines.
(Multiple Choice)
4.9/5
(69)
The ____ shows the intersection of the existing and new foundation and floor systems.
(Multiple Choice)
4.9/5
(80)
Building permits required for a remodel or addition include the structural, electrical, plumbing, and mechanical permits.
(True/False)
4.9/5
(90)
New crawl access, new vents, and new hold down and connectors required for lateral bracing should be represented on the _____.
(Multiple Choice)
4.8/5
(87)
A ____ is a useful tool to provide support while sketching and placing field notes.
(Multiple Choice)
4.8/5
(74)
The framing plan for a remodel is similar to the framing plan required for new construction.
(True/False)
4.9/5
(76)
Which of the following should be represented on the sections?
(Multiple Choice)
4.9/5
(84)
Structures built prior to the 1940s are most likely made using western platform construction.
(True/False)
4.8/5
(67)
The ____ for a remodel must show the size of the job site, the street, easements, setbacks, and the footprint of the existing structure, including decks.
(Multiple Choice)
4.9/5
(71)
The ____ plan shows the existing walls and materials to be removed to prepare the site for the new project.
(Multiple Choice)
4.9/5
(77)
A permit is required to construct, enlarge, alter, move, or demolish any one- or two-family dwelling or similar structure.
(True/False)
4.7/5
(86)
An addition is defined by the IRC a existing structure caused by increasing the existing floor area or by increasing or altering the height of a structure.
(True/False)
4.8/5
(66)