Exam 7: Managing Risk
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection101 Questions
Exam 3: Organization: Structure and Culture102 Questions
Exam 4: Defining the Project112 Questions
Exam 5: Estimating Project Times and Costs95 Questions
Exam 6: Developing a Project Schedule128 Questions
Exam 7: Managing Risk105 Questions
Exam 8: Scheduling Resources and Costs114 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager98 Questions
Exam 11: Managing Project Teams103 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations102 Questions
Exam 13: Progress and Performance Measurement and Evaluation98 Questions
Exam 14: Project Closure97 Questions
Exam 15: Agile Project Management94 Questions
Exam 16: International Projects103 Questions
Select questions type
Contingency funding is made up of contingency reserves and management reserves.
(True/False)
4.8/5
(78)
A Risk Response Matrix contains all of the following EXCEPT
(Multiple Choice)
4.7/5
(71)
One of the choices below refers to major unforeseen risks and endeavors to supply funds for the same. Which choice is it?
(Multiple Choice)
4.7/5
(73)
The event or point in time when a contingency plan will be implemented is called a(n) _________.
(Multiple Choice)
5.0/5
(79)
The risk management tool that is divided into three color-coded zones representing major, moderate, and minor risks is the risk
(Multiple Choice)
4.9/5
(90)
Adopting proven technology instead of experimental technology in order to eliminate technical failure would be an example of which risk response?
(Multiple Choice)
4.8/5
(81)
Although most risks are presented as something not desirable, there can also be desirable risks called Opportunities.
(True/False)
4.8/5
(85)
A list of questions that address traditional areas of uncertainty on a project is termed a
(Multiple Choice)
4.9/5
(82)
Including the change control system within the ________ is a key to a successful project.
(Multiple Choice)
4.9/5
(88)
When considering risk response development, changing the plan to eliminate the risk or condition is known as ____________ the risk.
(Multiple Choice)
4.9/5
(79)
The table that shows each risk event as rows while columns will identify the name of the risk, the response to the risk, the contingency plan and the trigger is called what?
(Multiple Choice)
5.0/5
(83)
Performance bonds, warranties, and guarantees are financial instruments used to share risk.
(True/False)
4.7/5
(70)
What kind of plan goes into place should a risk event actually occur?
(Multiple Choice)
5.0/5
(69)
An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is known as a __________.
(Multiple Choice)
4.7/5
(81)
This response is used when an identified opportunity is not actively pursued.
(Multiple Choice)
4.8/5
(78)
A ____________ is an alternative that will be used if a possible foreseen risk event becomes a reality.
(Multiple Choice)
4.7/5
(76)
________ reserves are controlled by the project manager and the owner of the project and are used to cover major unforeseen risks to the entire project.
(Multiple Choice)
4.8/5
(77)
The risk associated with the unlikelihood that one of the key members will be struck by lightning would most likely be handled by which of the following?
(Multiple Choice)
4.8/5
(69)
Which of the following is NOT one of the steps in the risk management process?
(Multiple Choice)
4.9/5
(71)
The first step in the risk management process is risk assessment.
(True/False)