Exam 14: Short-Term Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

One of the major limitations of the Gantt load chart is that it doesn't account for production variability such as unexpected breakdowns or human errors.

(True/False)
4.9/5
(71)

Earliest due date is a shop floor dispatching (sequencing) rule that relates the time available to complete a job to the amount of work left to be completed.

(True/False)
4.9/5
(74)

What are some limitations of rule-based scheduling systems?

(Essay)
4.9/5
(74)

Five welding jobs are waiting to be processed. Their processing times and due dates are given below. Using the critical ratio dispatching rule, in which order should the jobs be processed? All dates are specified as days from today. Five welding jobs are waiting to be processed. Their processing times and due dates are given below. Using the critical ratio dispatching rule, in which order should the jobs be processed? All dates are specified as days from today.

(Multiple Choice)
4.8/5
(80)

Short-term scheduling is important to efficiency and to cost reduction, but its impact is not of strategic importance.

(True/False)
4.7/5
(85)

Using SPT priority would result in what sequence for Jobs A, B, C, and D if their process times are 4, 6, 5, and 2 respectively?

(Multiple Choice)
4.9/5
(72)

Alaska Airlines uses mathematical short-term scheduling techniques and a high-tech Flight Operations Department to manage the rapid rescheduling necessary to cope with weather delays and similar disruptions.

(True/False)
4.8/5
(73)

A work center had actual input of 280 hours and actual output of 290 hours. What is the change in backlog?

(Multiple Choice)
4.9/5
(86)

A recent advance in short-term scheduling that makes use of expert systems and simulation in solving dynamic scheduling problems is:

(Multiple Choice)
4.9/5
(73)

The assignment method provides an optimum, one-to-one assignment of jobs to resources.

(True/False)
4.9/5
(83)

Orders are processed in the sequence in which they arrive if (the) ________ rule sequences the jobs.

(Multiple Choice)
4.8/5
(71)

Which critical ratio value implies that a job is already late?

(Multiple Choice)
4.8/5
(88)

In services, the scheduling emphasis is usually on materials rather than staffing levels.

(True/False)
4.9/5
(101)

Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the earliest due date dispatching rule, in which order should the jobs be processed? Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the earliest due date dispatching rule, in which order should the jobs be processed?

(Multiple Choice)
4.7/5
(83)

The constant work-in-process (ConWIP) card aids input-output control by limiting the amount of work in a work center.

(True/False)
4.7/5
(83)

A manufacturer has the following jobs waiting on a single work center. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Processing time in 15-minute time blocks and due date for each job are in the table below. A manufacturer has the following jobs waiting on a single work center. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Processing time in 15-minute time blocks and due date for each job are in the table below.    (a) Complete the following table. Show your supporting calculations below. (b) Which dispatching rule has the best score for flow time? for work in process (jobs in the system)? for lateness? (c) Is there ANY sequence that can avoid all lateness? Explain or provide an example.   (a) Complete the following table. Show your supporting calculations below. (b) Which dispatching rule has the best score for flow time? for work in process (jobs in the system)? for lateness? (c) Is there ANY sequence that can avoid all lateness? Explain or provide an example. A manufacturer has the following jobs waiting on a single work center. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Processing time in 15-minute time blocks and due date for each job are in the table below.    (a) Complete the following table. Show your supporting calculations below. (b) Which dispatching rule has the best score for flow time? for work in process (jobs in the system)? for lateness? (c) Is there ANY sequence that can avoid all lateness? Explain or provide an example.

(Essay)
4.8/5
(82)

Briefly describe how "the unexpected" makes short-term scheduling at Alaska Airlines a challenge. Also describe how Alaska Airlines meets that challenge and achieves competitive advantage through short-term scheduling.

(Essay)
4.9/5
(66)

What is the difference between a Gantt load chart and a Gantt scheduling chart?

(Essay)
4.8/5
(86)

Which of the following dispatching rules tends to minimize job flow time?

(Multiple Choice)
5.0/5
(78)

A Gantt load chart shows the loading and idle time of several departments, machines, or facilities.

(True/False)
5.0/5
(82)
Showing 61 - 80 of 124