Exam 21: Learning Curves

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Learning curves can only be applied to labor.

(True/False)
4.8/5
(83)

Suppose that there are two products with the same first product time. However, product A has an improvement rate of 10% while product B has an improvement rate of 15%. How much longer will it take to make the 10th unit of product A compared to product B?

(Multiple Choice)
4.8/5
(78)

A certain product under development took 200 hours for the production of its 2nd unit and 160 hours for its 4th unit. (a) What is the learning curve? (b) How much time did the first unit take? (c) How much time would the production of the 10th unit take? (Use both the formula and the Table E.3 approach. Do the two versions agree?)

(Essay)
4.9/5
(80)

Which of the following is a limitation of the use of learning curves?

(Multiple Choice)
4.8/5
(65)

What cautions are in order when using learning curves?

(Essay)
4.8/5
(84)

What can cause a learning curve to vary from a smooth downward slope?

(Essay)
4.9/5
(66)

Which of the following statements regarding the usefulness of learning curves is FALSE?

(Multiple Choice)
4.7/5
(71)

The first unit took 10 hours and the fourth unit took 8.1 hours to complete. What is the learning curve?

(Multiple Choice)
4.9/5
(78)

If the learning curve for a process is 100 percent, then each unit in a series of units will have the same labor requirements.

(True/False)
4.8/5
(90)

Because learning curves do not vary much from company to company in the same industry, managers can apply other company's learning rates as good estimates.

(True/False)
4.9/5
(71)

Which one of the following courses of actions would NOT be taken by a firm wanting to pursue a learning curve steeper than the industry average?

(Multiple Choice)
4.9/5
(74)

An 80% learning curve means that with each unit increase in production, labor requirements fall by 20%.

(True/False)
5.0/5
(70)

Your firm has expertise with a special type of hand-finished furniture. The learning curve is known to be 82%. If the first piece of furniture took 6 hours, how long will it take to make the second? How long will it take to make the fourth?

(Essay)
4.8/5
(81)

The first unit of a product took 832 hours to build, and the learning curve is 90%. How long will it take to make the 25th unit? (Use at least three decimals in the exponent if you use the formula approach.)

(Multiple Choice)
4.7/5
(65)

The first unit took 10 hours and the fourth unit 8.1 hours. What is the improvement rate?

(Multiple Choice)
4.8/5
(85)

A 100% learning curve implies that:

(Multiple Choice)
5.0/5
(89)

The learning curve for a product is 70 percent. The first unit took 100 hours to complete. The manufacturer wants to determine how many hours the fifth unit will take by using the formula approach. What is the coefficient b for that calculation?

(Multiple Choice)
4.9/5
(75)

A job with a 90% learning curve required 20 hours for the initial unit. The eighth unit should require approximately how many hours?

(Multiple Choice)
4.9/5
(93)

A metal works fabricator is about to release a new model of his firm's copper sculpture and fountain. The operations manager estimates that this product is subject to a 90 percent learning curve on labor only-the material bill is not affected by experience. The firm prices its work based on cost-the sum of materials plus 30 percent and labor plus 50 percent. (This allows the firm to practice a form of "demand management" for its very popular works.) The first item has already been finished; the material bill was $800 and labor totaled 40 hours. The firm pays its metalworking artisans an average of $18 per hour. What should be the asking price of the first unit? The second?

(Essay)
4.8/5
(94)

Sally suspects strongly that there is a learning curve associated with solving problems assigned for operations management. She notes that it took her approximately 33 minutes to solve the first problem and 20 minutes to solve the fifth problem. (a) Estimate Sally's learning curve. (b) Using your answer from part (a), estimate how much longer it will take Sally to finish the three problems that remain.

(Essay)
4.9/5
(74)
Showing 21 - 40 of 114