Exam 12: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The standard deviation of the critical path is equal to the sum of the standard deviations of all of the tasks on the critical path.

(True/False)
4.8/5
(80)

Key phases in a project time line are often referred to as milestones.

(True/False)
5.0/5
(82)

Developing the preliminary project scope statement is a key activity during which phase of a project?

(Multiple Choice)
4.9/5
(69)

Tasks not on the critical path have a slack time equal to zero.

(True/False)
4.7/5
(78)

Developing the project charter is a key activity during which phase of a project?

(Multiple Choice)
4.7/5
(72)

Developing the project charter is a key activity during the planning phase of a project.

(True/False)
4.9/5
(89)

The project team stage of development when the team members get to know each other,however,agreements have not yet been made to facilitate smooth interaction between team members,is

(Multiple Choice)
4.7/5
(78)

The best estimate for the time required to complete a project task is known as ________.

(Short Answer)
5.0/5
(84)

Allowing the deliverables of a project to expand over time is known as ________.

(Short Answer)
4.8/5
(71)

The project planning step of estimating activity times is done before determining the work breakdown structure of a project.

(True/False)
4.9/5
(79)

As per Hersey and Blanchard's Situation Leadership Model,which role of a manager can be described as Low Task Behavior and Low Relationship Behavior?

(Multiple Choice)
4.9/5
(78)

The earliest finish time for a task is equal to the latest finish time minus the task time.

(True/False)
4.9/5
(80)

Task C is directly preceded by two tasks-task A and task B.Task A has an expected task completion time of five weeks and an ES time of week 6.Task B has an expected task completion time of seven weeks and an ES time of week 7.Task C has an expected task completion time of 10 weeks.The ES for activity C is week

(Multiple Choice)
4.9/5
(96)

The project charter is most likely to include the project goals,scope and deliverables.

(True/False)
4.9/5
(72)

Specialists that are assigned full-time to a project that needs to be completed quickly are known as ________ team(s).

(Short Answer)
4.8/5
(93)

The longest foreseeable task completion time is known as pessimistic completion time.

(True/False)
4.9/5
(69)

The formula which helps compute project times with a high probability of completion is known as ________.

(Short Answer)
4.9/5
(73)

An organizational form in which an employee works part-time on a project team and continues to perform fundamental job assignments is known as ________ structure.

(Short Answer)
4.8/5
(85)

Given the portion of the network diagram shown below,where numbers in boxes show the task times,what is the earliest finish time for task C,if the earliest start time for task A is 10,and the earliest start time for task B is 13? Given the portion of the network diagram shown below,where numbers in boxes show the task times,what is the earliest finish time for task C,if the earliest start time for task A is 10,and the earliest start time for task B is 13?

(Multiple Choice)
4.9/5
(84)

As per the Project risk/return matrix,projects that are low-hanging fruit have a

(Multiple Choice)
4.9/5
(88)
Showing 61 - 80 of 90
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)