Exam 5: Inventory Management
Exam 1: Creating Customer Value through Operations128 Questions
Exam 2: Supply Chain Management171 Questions
Exam 3: Process Configuration137 Questions
Exam 4: Capacity145 Questions
Exam 5: Inventory Management177 Questions
Exam 6: Quality and Process Improvement240 Questions
Exam 7: Lean Systems158 Questions
Exam 8: Managing Projects153 Questions
Exam 9: Location and Layout217 Questions
Exam 10: Managing Demand and Forecasting189 Questions
Exam 11: Operations Planning and Scheduling138 Questions
Exam 12: Resource Planning174 Questions
Exam 13: Decision Making82 Questions
Exam 14: Financial Analysis41 Questions
Exam 15: Work Measurement98 Questions
Exam 16: Learning Curve Analysis44 Questions
Exam 17: Computer-Integrated Manufacturing53 Questions
Exam 18: Acceptance Sampling Plans71 Questions
Exam 19: Simulation36 Questions
Exam 20: Special Inventory Models33 Questions
Exam 21: Linear Programming57 Questions
Exam 22: Waiting Lines109 Questions
Select questions type
________ is the lot size that minimizes total annual inventory holding and ordering costs.
(Short Answer)
4.9/5
(77)
A(n)________ system is a visual system in which an item's inventory is stored at two different locations.
(Short Answer)
4.8/5
(70)
________ inventory is the portion of total inventory that varies directly with lot size.
(Short Answer)
4.9/5
(73)
The degree at which all the work can be done is referred to as repeatability.
(True/False)
4.9/5
(78)
Table 5.9
Demand = 140 units/week
Standard deviation in weekly demand units
Ordering cost /order
Holding cost per unit per year
Cycle-service level percent
Lead time weeks
You will need to refer to a normal table to answer the question(s).
-Use the information in Table 5.9.Design a continuous review system making Q equal to EOQ.What will be the economic order quantity (EOQ)?
(Multiple Choice)
4.9/5
(74)
Which one of the following descriptions of a base-stock system is best?
(Multiple Choice)
4.9/5
(91)
Jan Tuttle is the inventory manager of an art supply store.She uses a periodic review system for all oil paints.The number of periods between orders (P)for red #69 is 15 workdays.(The store operates 50 weeks/year,5 workdays/week.)Additional information concerning red #69 follows.
Demand = 30 units/workday
Standard deviation of daily demand = 4 units/workday
Lead time = 7 workdays
Desired cycle-service level = 85%
A normal table is appended to this exam.What is the target inventory level T for red #69?
(Multiple Choice)
5.0/5
(85)
Explain the meaning and significance of the cycle-service level in managing inventory.
(Essay)
4.9/5
(93)
Sensitivity analysis on the economic order quantity (EOQ)formula can help the operations manager answer several questions on how to manage inventories.Which one of the following questions is NOT answered by EOQ sensitivity analysis?
(Multiple Choice)
4.9/5
(92)
Table 5.4
A company operating under a continuous review system has an average demand of 50 units per week for the item it produces. The standard deviation in weekly demand is 20 units. The lead time for the item is 6 weeks, and it costs the company $30 to process each order. The holding cost for each unit is $10 per year. The company operates 52 weeks per year. You will need to refer to a normal table to answer the question(s).
-Use the information in Table 5.4.What is the reorder point if the company finally decides to have a 95 percent cycle-service level?
(Multiple Choice)
4.8/5
(77)
An assistant manager is reviewing the costs associated with the store's best-selling product.The data available follows:
Demand = 2000 units/year
Order cost = $80/order
Holding cost = $10/unit/year
a.The current order quantity is 125 units per order.What is the total annual ordering cost and holding cost for this order size?
b.What would be the EOQ and its associated ordering and holding cost?
(Essay)
4.8/5
(65)
________ is the cost of preparing a purchase order for a supplier or a production order for the shop.
(Short Answer)
4.9/5
(87)
Safety stock is only used in continuous review (Q)inventory systems,not in periodic review (P)inventory systems.
(True/False)
4.8/5
(77)
Your firm uses a continuous review system (Q system),where the inventory position is updated after every transaction.The firm operates 52 weeks per year.One of the items has the following characteristics:
Demand = 14,560 units per year
Ordering cost = $40 per order
Holding cost = $6 per unit per year
Lead time = 2 weeks
Standard deviation in weekly demand = 100 units
Cycle-service level = 80 percent
If Q is made equal to the EOQ,what are the desired values for Q and R?
(Multiple Choice)
4.9/5
(82)
Holding inventory towards the finished goods level supports lower costs but also results in longer delivery times.
(True/False)
4.8/5
(74)
Showing 161 - 177 of 177
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)