If a project has exactly one critical path,which of the following statements is TRUE?


A) Crashing an activity on the critical path will always result in an increase in total project profits.
B) Activities on the critical path cannot be crashed.
C) Crashing an activity on the critical path will always result in a reduced total project completion time.
D) The best schedule is one in which all activities are crashed as much as possible.