Multiple Choice
Scenario 9.12
Demand = 50,000 units/week
Standard deviation of weekly demand = 15,000 units
Average lead time = 8 weeks
Standard deviation of lead time: 3 weeks
Cycle-service level = 80%
A continuous review system is used to control inventory.
A normal distribution table is appended to this exam.
-Use the information in Scenario 9.12.What reorder point should the firm use for this product?
A) greater than 0 but less than or equal to 150,000 units
B) greater than 150,000 units but less than or equal to 300,000 units
C) greater than 300,000 units but less than or equal to 400,000 units
D) greater than 400,000 units but less than or equal to 500,000 units
E) greater than 500,000 units
Correct Answer:

Verified
Correct Answer:
Verified
Q14: _-demand items are items for which demand
Q57: _ inventory is the portion of total
Q59: Inventory management is the planning and controlling
Q72: Which one of the following statements regarding
Q87: In an EOQ model, as the annual
Q101: Scenario 9.7<br>You are the operations manager of
Q102: The number of setups (or orders) per
Q108: Scenario 9.11<br>The Hastings Company is a nation-wide
Q109: Scenario 9.9<br>Demand = 5,200 units/year<br>Standard deviation of
Q153: Dependent demand items are those items for