Multiple Choice
Scenario 9.12
Demand = 50,000 units/week
Standard deviation of weekly demand = 15,000 units
Average lead time = 8 weeks
Standard deviation of lead time: 3 weeks
Cycle-service level = 80%
A continuous review system is used to control inventory.
A normal distribution table is appended to this exam.
-Use the information in Scenario 9.12.What is the standard deviation of demand during lead time?
A) greater than 0 but less than or equal to 100,000 units
B) greater than 100,000 units but less than or equal to 200,000 units
C) greater than 200,000 units but less than or equal to 300,000 units
D) greater than 300,000 units
Correct Answer:

Verified
Correct Answer:
Verified
Q6: The primary reason for keeping inventories low
Q7: Scenario 9.2<br>The Burdell Company is a small
Q11: Scenario 9.1<br>The Talbot Company uses electrical assemblies
Q17: Which one of the following statements concerning
Q37: What is a two-bin system and how
Q60: Cycle counting is an inventory-control method whereby
Q86: A(n) _ system is a visual system
Q111: A(n) _ is an order that cannot
Q118: If on-hand inventory = 100 units, scheduled
Q161: What is a base-stock system?