Multiple Choice
Figure 3-3
The Sandoval Company has four process engineers that are each able to process 1,500 design changes. Last year 5,250 design changes were produced by the four engineers. Each engineer is paid $60,000 per year
-Refer to Figure 3-3. Calculate the unused capacity.
A) 750 change orders
B) 1,375 change orders
C) 4,000 change orders
D) 2,000 change orders