The Amount of Overhead Applied to Jobs Using a Predetermined

Question 40

Multiple Choice

The amount of overhead applied to jobs using a predetermined (budgeted) rate is rarely equal to the actual cost of overhead incurred for a period. Which of the following is not a valid explanation for this?


A) Actual spending for overhead is not equal to budgeted spending for overhead.
B) Actual use of the overhead allocation base is not equal to the budgeted use of the allocation base.
C) Budget estimates of overhead were unrealistically low.
D) Direct costs were unexpectedly high.