Multiple Choice
If the engineer worked for 20 hours on a job,Z,and the rates were overhead 125 per cent on direct labour cost and the direct labour rate was $25 per hour,what is the total cost of the job?
A) $500
B) $625
C) $1000
D) $1125
Correct Answer:

Verified
Correct Answer:
Verified