Atrex Company determined that its variable overhead spending variance was $10 000 unfavourable for the year. Actual variable overhead was $100 000 for the year. Variable overhead is applied based on machine hours. The standard rate per machine hour was $9. The standard quantity of machine hours allowed for good output was 9000. What was the actual quantity of machine hours used?
A) 12 222
B) 11 000
C) 10 000
D) 9000
Correct Answer:

Verified
Correct Answer: