Multiple Choice
The production schedule in units:
A) Cannot be prepared until the budgeted income statement is completed.
B) Is dependent upon the sales forecast for the period.
C) Is based upon the manufacturing cost budget,that is,upon the level of funds available for manufacturing costs.
D) Is the starting point in the preparation of the master budget.