Which of the following probably is NOT a timeboxing step?
A) Set the date for system delivery
B) Prioritize the functionality that needs to be included in the system
C) Build the core of the systems (with the basic functions included)
D) Add sufficient staff to reach basic functionality
E) Postpone functionality that cannot be provided with in the time frame
Correct Answer: