The Charade Company is preparing its Manufacturing Overhead budget for the fourth quarter of the year. The budgeted variable factory overhead is $5.00 per direct labor-hour; the budgeted fixed factory overhead is $75,000 per month, of which $15,000 is factory depreciation.
-If the budgeted direct labor time for November is 7,000 hours, then the total budgeted factory overhead for November is:
A) $95,000
B) $110,000
C) $75,000
D) $125,000
Correct Answer: