Multiple Choice
Zike Corporation's static planning budget for October appears below.The company bases its budgets on machine-hours.
In October,the actual number of machine-hours was 6,000,the actual supplies cost was $14,740,the actual power cost was $49,170,the actual salaries cost was $15,390,and the actual equipment depreciation was $63,670. The spending variance for power cost in the performance report for the month should be:
A) $3,570 U
B) $1,170 U
C) $3,570 F
D) $1,170 F
Correct Answer:

Verified
Correct Answer:
Verified
Q17: An unfavorable labor rate variance can occur
Q106: Longview Hospital performs blood tests in its
Q108: Gilder Corporation makes a product with the
Q109: Vangemert Corporation uses customers served as its
Q113: Letts Corporation manufactures and sells a single
Q166: Pearle Corporation makes automotive engines. For the
Q197: A flexible budget can be used to
Q238: A spending variance is the difference between
Q264: Capilla Urban Diner is a charity supported
Q287: An unfavorable spending variance may reflect waste