Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed:
During March, the laboratory performed 2,000 core tests. On March 1 no direct materials (sand) were on hand. Variable manufacturing overhead is assigned to core tests on the basis of direct labour hours. The following events occurred during March:
8,600 pounds of sand were purchased at a cost of £7,310.
7,200 pounds of sand were used for core tests.
840 actual direct labour hours were worked at a cost of £8,610.
Actual variable manufacturing overhead incurred was £3,200.
-
The labour efficiency variance for March is
A) £480 favourable.
B) £480 unfavourable.
C) £192 favourable.
D) £192 unfavourable.
Correct Answer:

Verified
Correct Answer:
Verified
Q53: The Wright Company has a standard
Q54: If variable manufacturing overhead is applied on
Q55: Analyse the problems illustrated by the scenario
Q56: A favourable material price variance coupled with
Q57: An unfavourable material quantity variance indicates that
Q58: The material price variance is computed by
Q59: If managers are insensitive and use variances
Q60: Variable manufacturing overhead is applied to products
Q62: The following labour standards have been
Q63: The entry to record unfavorable labour efficiency