Cox Engineering Performs Cement Core Tests in Its Laboratory During March, the Laboratory Performed 2,000 Core Tests
Multiple Choice
Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed:
During March, the laboratory performed 2,000 core tests. On March 1 no direct materials (sand) were on hand. Variable manufacturing overhead is assigned to core tests on the basis of direct labour hours. The following events occurred during March:
8,600 pounds of sand were purchased at a cost of £7,310.
7,200 pounds of sand were used for core tests.
840 actual direct labour hours were worked at a cost of £8,610.
Actual variable manufacturing overhead incurred was £3,200.
-
The materials quantity variance for March is
A) £900 favourable.
B) £1,950 favourable.
C) £1,950 unfavourable.
D) £ 900 unfavourable.
Correct Answer:

Verified
Correct Answer:
Verified
Q45: Management by exception can blind management from
Q46: List the 'pros' and 'cons' of using
Q47: The Geurtz Company uses standard costing. The
Q48: Standards are set for units; budgets are
Q49: Ideal standards should be used for forecasting
Q51: The following standards for variable manufacturing
Q52: An unfavourable direct labour efficiency variance could
Q53: The Wright Company has a standard
Q54: If variable manufacturing overhead is applied on
Q55: Analyse the problems illustrated by the scenario