Cox Engineering Performs Cement Core Tests in Its Laboratory During March, the Laboratory Performed 2,000 Core Tests
Multiple Choice
Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed:
During March, the laboratory performed 2,000 core tests. On March 1 no direct materials (sand) were on hand. Variable manufacturing overhead is assigned to core tests on the basis of direct labour hours. The following events occurred during March:
8,600 pounds of sand were purchased at a cost of £7,310.
7,200 pounds of sand were used for core tests.
840 actual direct labour hours were worked at a cost of £8,610.
Actual variable manufacturing overhead incurred was £3,200.
-
The materials price variance for March is
A) £860 unfavourable.
B) £860 favourable.
C) £281 unfavourable.
D) £281 favourable.
Correct Answer:

Verified
Correct Answer:
Verified
Q10: In some cases a favourable variance can
Q11: Standard Costing is not worth bothering with
Q12: The Cox Company uses standard costing.
Q13: The following labour standards have been
Q14: The Geurtz Company uses standard costing. The
Q16: The following labour standards have been
Q17: Palo Corp. manufactures one product with a
Q18: Generally speaking, it is the responsibility of
Q19: Home Company manufactures tables with vinyl tops.
Q20: The Swenson Company has a standard