Multiple Choice
The predetermined overhead rate for manufacturing overhead for 2012 is $4.00 per direct labor hour.Employees are expected to earn $5.00 per hour and the company is planning on paying its employees $100,000 during the year.However,only 75% of the employees are classified as "direct labor." What was the estimated manufacturing overhead for 2012?
A) $60,000.
B) $75,000.
C) $80,000.
D) $93,750.