A Continuous (Rolling)budget

Question 65

Multiple Choice

A continuous (rolling) budget:


A) presents the plan for a range of activity so that the plan can be adjusted for changes in activity levels.
B) presents a statement of expectations for a period of time but does not present a firm commitment.
C) presents the plan for only one level of activity and does not adjust to changes in the level of activity.
D) drops the current month or quarter and adds a future month or quarter as the current month or quarter is completeD.