If all other factors specified in an attributes sampling plan remain constant, changing the specified tolerable rate from 6% to 10%, and changing the specified risk of assessing control risk too low from 3% to 7% would cause the required sample size to:
A) Increase.
B) Remain the same.
C) Decrease.
D) Change by 4%.