Multiple Choice
Under the percentage-of-completion method, a company has recognized $40,000 of profit through to the beginning of the current year on a contract, and total estimated contract cost is $500,000 at that time. The contract price is $800,000. What is the percent of completion at the beginning of the current year?
A) 13.33%
B) 15.8%
C) 8%
D) Insufficient data