Multiple Choice
A construction company uses the percentage-of-completion method for long-term construction contracts. A particular job was begun in 2006 and completed 2008. During 2007, it appeared that the project would cost 25 percent more than originally expected. Data at each year-end are given below: The contract price was $700,000. Assuming the company properly recorded income in 2006, how much income should be recorded in 2007?
A) $10,000
B) $42,000
C) $160,000
D) $192,000